Energy Department (Jaipur Vidhyut Vitran Nigam Limited)
Below is an indicative list of approvals required with time-frame for starting a business in Rajasthan:
| S.No. | Permissions/Clearances | Time Limit (Within working days) |
| Release of Power connection |
||
| 1. |
For loads up to 25 kw |
|
| 21 days from receipt of application | ||
| 30 days after compliance of Demand Notice if no augmentation is required, otherwise 45 days | ||
| 2. |
For loads above 25 kw and up to 300 kw |
|
| 21 days from receipt of application | ||
| 60 days after compliance of Demand Notice | ||
| 3. |
For loads above 300 kw and up to 2000 kw |
|
| 21 days from receipt of application | ||
| 60 days after compliance of Demand Notice | ||
| 4. |
For loads above 2000 kw and up to 3000 kw |
|
| 21 days from receipt of application | ||
| 60 days after compliance of Demand Notice | ||
| 5. |
For loads above 3000 kw and up to 5000 kw |
|
| 21 days from receipt of application | ||
| 120 days after compliance of Demand Notice | ||
For details, please visit the official Single Window System Website: www.bipraj.raj.nic.in