Below is an indicative list of approvals required with time-frame for starting a business in Rajasthan:
| S.No. | Permissions/Clearances | Time Limit (Within working days) |
| 1. | Sanction of loan | 40 days |
| 2. |
Allotment of plots in Industrial Areas |
40 days |
| 3. |
Issue of NOC to the authority concerned regarding conversion of land use of the agriculture land at Unit Office Level |
15 days |
| 4. |
Transfer permission in case of sale of plot by the allottee at Unit Office Level |
15 days |
| 5. |
Transfer permission in case of death of the plot holder at Unit Office Level |
15 days |
| 6. |
Compounding of unauthorized constructions in an allotted plot at Unit Office Level |
15 days |
| 7. |
Allotment/Regularization of strip of land/excess land at Unit Office Level |
15 days |
| 8. |
Extension of time period for payment of development charges: |
|
| 15 days | ||
| 25 days | ||
| 9. |
Extension of time period for making utilization of the allotted plot (completion of the project): | |
| 15 days | ||
| 25 days | ||
| 10. |
Permission to sub-divide the allotted plot at Head Office Level |
45 days |
| 11. |
Conversion/change in land use of an allotted plot at Head Office Level |
30 days |
| 12. |
Relaxation in set-backs: |
|
| 15 days | ||
| 30 days |
For details, please visit the official Single Window System Website: www.bipraj.raj.nic.in